Project Schedule

Project Schedule


Public Involvement -- April 2006 thru September 2007
Conceptual Analysis
-- February 2006 thru October 2006
Preliminary Design -- October 2006 thru February 2007
Final Design -- March 2007 thru September 2007
Property Acquisition -- June 2007 thru November 2007
Advertising, Bid and Award (2008) -- February 2008 thru April 2008
Construction (2008) -- May 2008 thru September 2008
Advertising, Bid and Award (2009) -- February 2009 thru April 2009
Construction (2009) -- May 2009 thru September 2009